Location: 11000 Cedar Avenue, Third Floor
Client: Case School of Engineering
Schedule:
- Design: Dec 2022 - May 2023
- Construction: Aug 2023 - April 2024
- Beneficial Occupancy Date (BOD): 4.24.24
Financials:
- Budget: $9.3M
- Total Project Cost: $8.2M
Scope of Project: In addition to mechanical, electrical, and plumbing upgrades, the space was outfitted with unique elements to support and enable research by the Human Fusions Institute. Specialized program components include a large robotics test arena, a submersible testing tank, presentation spaces equipped with advanced technology and enhancements to audiovisual and security systems throughout the facility.