Location: 2101 Martin Luther King Jr. Drive
Client: Case School of Engineering
Schedule:
- Design: Feb. 2022 – June 2023
- Construction: Aug. 2023 – Aug. 2024
- Beneficial Occupancy Date (BOD): 8.23.24
Financials:
- Budget: $6.6M
- Total Project Cost: $6.6M
Scope of Project: The interior renovations enhanced the student experience by creating dynamic spaces where students can collaborate, study and perform computational research. Additional interior alterations included upgrades to classrooms, office spaces, and restrooms on the renovated floors. The building’s exterior presence was improved by creating a vibrant, inviting and intuitive entry sequence and incorporating new landscaping and hardscapes.