Wade Park Community Engagement Center

Location: 11300 Wade Park Avenue, Cleveland

Client: ÐÓ°ÉÊÓÆµ Local Government and Community Relations

Schedule: 

  • Design:  March 2023 – June 2023
  • Construction:  November 2023 – August 2024
  • Beneficial Occupancy Date (BOD): 8.28.2024

Financials:

  • Budget: $2.3M
  • Total project cost: $2.37M

Scope of Project: The second-floor porch addition and the exterior door on the third floor were removed, while the interior was completely renovated to accommodate new community outreach programming. This space features offices for full-time CWRU staff, along with meeting and community areas. A new parking lot with lighting, an accessibility ramp made of composite wood with metal rails, and updated landscaping was also added.